This PUSD Witter Field Renovation Project Update Letter 6.22.2023 provides an update from Pete Palmer, PUSD Director of Facilities/Construction Manager, on construction safety requirements for temporary parking restrictions, and Winsor driveway gate closures, as well as addressing drainage calculations.
Look Ahead Schedule Highlights - see full schedule here.
Field Turf - Removal & Off-haul 6/15-6/28
Bleacher - Demo & Off-haul 6/12-6/23
Field Excavation & Off-haul 6/29 -7/6
Storm Drainage 7/7-7/27
PHS Track & Field Drainage - Verde Design
PHS Track & Field Reconstruction Project - Verde Design